Description
Solar Panel Production Line
Compressed Air:
Pressure: minimum 8 bar steady
Quality: dryed, oilfree
Reservoir in L : 200
Productiontemperature:
22C° - 24C°
Powersupply:
Voltage: 230VAC, 400VAC
Frequence: 50HZ
Phases: L1/L2/L3/N/PE
Range: max. 10V DEVIATION
Total KVA: 250
Nitrogen:
lpm: 15
kpa: min. 275
The Line Mainly Comprise Following Equipment:
600 cells / h stringer refurbished
Automated cell loading and ribbon placement
Automated layup in boxes
Manual Foil Cutter
Manual cutting of the foil
With two rolls for EVA and backsheet
Fully automated Layup 90 MW
Automated centering of the strings
Automated placement of the strings
Foil Piacing Station
Manual station to place lamination foil
Inline station
Manual Busing Station
With two soldering stations
Laminator Refurbished - 2 Panels / Cycle
For up to 2 panels per cycle (72 celt design)
Tape Aplicator
Placing tape on the faminate
Manual tool
Trim Station - Lifter
Lifting up the laminate
360° turn table
Frame Station Semi
J-Box Station
Final Optical Inspectiog
Check for optical defects
With camera and screen
LED Flasher
More than 2 million flashes without changing the LED lamps
For panels with 2x x 1m
Hi-Pot Test
High potential test
According TÜV standard procedure
Please note that this description may have been translated automatically. Contact us for further information. The information of this classified ad are only indicative. We recommend to check the details with the seller before a purchase